JACKSONVILLE REPLACES ABOUT 260 LEAD WATER LINES, PREPARES EAST-SIDE WORK

From the Eagle Valley Bank 24-Hour News Center •
EPA file photo showing a lead service line connection
A lead service line connection shown in an EPA file photo.

JACKSONVILLE, Ill. — Jacksonville has replaced about 260 lead water service lines in the first phase of a citywide project and is preparing to bid a second round of work on the east side. Construction is expected to start in spring 2027.

The city originally sought bids for 245 replacements in the first phase. Project engineer Ben Spreen of Benton Engineering said the city completed about 15 more within the original bid amount. Crews also found that some lines initially identified as lead were made of another material.

The next phase is expected to cost about $6 million. More than $4 million is expected to come from financing the city will not have to repay, with more than $1.8 million financed through a no-interest loan. The broader replacement program is expected to run in 10 phases and cost about $30 million.

Homeowners who receive a permission form from the city need to sign and return it so crews can enter their property to replace the line. The city is preparing the bid for phase two. A contractor and exact start date have yet to be announced.

The Illinois EPA’s fiscal 2026 project list described the second phase as roughly 254 replacements. The east-side work area extends roughly from Dunlap Street to Morton Avenue and east of West Street, according to project engineer Ben Spreen. The project boundaries are approximate. Households should look for the city’s entry form to determine whether crews need access to their property.